ECE Offshore has signed a contract with Ballast Nedam Infra B.V. for the installation of the submarine power cables on Windplanblauw. The scope includes:

  • installation of 5 export cables and 19 inner-array grid cables
  • cable burial up to 2m depth
  • Bathymetric surveys
  • Pre-lay grapnel run

Works will be performed in Q1-Q2 2023.