ECE Offshore to install submarine power cables for Red Sea Project
ECE Offshore has been awarded a contract for the installation of three submarine power cables connecting three island that are part of the Red Sea Project in KSA. The scope includes:
- Mobilisation of cable lay vessel and trenching support vessel
- Installation of 56km of submarine power cable including six shore landing operations
- Pre-lay grapnel run operations
- Bathymetric / pre-lay survey
- Post lay cable burial
- Articulated pipe installation
Installation of the cables will find place in Q4 2022.